Asbestos Abatement Project Notification Details
Project # A9122-2026
Contractor: Steadfast Resources LLC
Contact Person: Tucker Runion
Contact Phone: (205) 546-0205
Project Site: Central Elementary School
611 Beasley Rd
Steele, MO 63877
Type: 10000sf n-f VCT Floor tile &mastic, 4000sf n-f mastic wall dots
Disposal Site: NEA Regional Solid Waste, 1810 Greene Rd 890, Paragould AR
Amendments: addtnl qnty: 6000sf flooring removed 6/19, revd air monitoring prof: Gary Snook; remaining 1000sf VCT, 4000sf mastic removed from scope and will remain in building to be removed at a later date;
Prior Use: School
Present Use: School
Branch Office: SERO
Start Date: 06/10/2026
Complete Date: 07/02/2023
Received Date: 05/27/2026
Comments: poss mechanical removal, report received 6/1/2026
Paid: Yes