Project # A9060-2026


Contractor: Wiedeman Dozing LLC
Contact Person: David Wiedeman
Contact Phone: (660) 651-5074

Project Site: Moberly Inn
1200 US Hwy 24
Moberly, MO 65270
Type: 4500sf frbl ceiling & wall txtr
Disposal Site: Maple Hill Landfill
Amendments: on hold 2/18; resume 2/19/2026; on hold 2/23 due to temp, resm 2/24; resume 2/24; resm 3/27, add qnty 616sf frbl ceiling txtr, report included, revd end 3/30/2026; on hold 3/27, resm 3/30, revd end 3/31; on hold 3/31; Revd end 4/3/2026;
Prior Use: Inn, Restaurant
Present Use: Inn, Restaurant
Branch Office: NERO

Start Date: 02/18/2026
Complete Date: 04/03/2026
Received Date: 02/02/2026

Comments: report received 2/9/2026. Unclear whether restaurant basement inspected, needs inspection for Bldg 3 before demolition of that bldg. Report for missing area received 3/25/2026;

Paid: Yes